Plan In Place For Taylorville High School Special Education Addition

Taylorville School Board has a plan in place moving forward for the construction schedule for the Taylorville High School new addition for its special education unit.  Site demolition is set to take place July 25th, with teams laying out the building pad July 26th-31st.  On August 1st and 2nd will be site water matters and internal electrical work will be done on the 2nd-4th of August.  Foundation walls are set to be placed on August 4th-11th.  Foundation walls will be backfilled on August 14th.

 

Plumbing and electrical work is set for August 15th-17th and the concrete slab will be poured on August 22nd and 23rd. This timeline may change given the weather and other circumstances.  The board also has asked the construction manager to look at possible cost reductions for the option chosen for the construction of the proposed gym and performing arts center. 

 

The next Taylorville School Board meeting is set for Tuesday, August 8th at 6 PM. 

Townhall Top of the Hour News

Weather - Sponsored By:

TAYLORVILLE WEATHER

Local News

Facebook Feed - Sponsored By: